Submit manuscript...
MOJ
eISSN: 2572-8520

Civil Engineering

Research Article Volume 4 Issue 4

Comparative cost analysis between interlocking bricks and sandcrete blocks for residential buildings in Ghana

Emmanuel Nana Jackson, Zakari Mustapha, Addobea Joyce Aburam, Jeriscot Henry Quayson

Department of Building Technology, School of Engineering, Cape Coast Technical University, Ghana

Correspondence: Zakari Mustapha, Department of Building Technology, School of Engineering, Cape Coast Technical University, Cape Coast, Ghana, P. O. Box AD.50, Cape Coast, Ghana, Tel 2335 0416 6674

Received: November 08, 2017 | Published: July 19, 2018

Citation: Jackson EN, Mustapha Z, Aburam AJ, et al.Comparative cost analysis between interlocking bricks and sandcrete blocks for residential buildings in Ghana. MOJ Civil Eng. 2018;4(4):206-211. DOI: 10.15406/mojce.2018.04.00120

Download PDF

Abstract

The extensive use of Sandcrete blocks (SBs) for residential buildings as compared to interlocking bricks (IBs) has significantly increased its cost and has therefore affected the cost of housing delivery in Ghana. The research aimed at comparing the cost of SBs and IBs for residential buildings in Ghana. The study adopted qualitative and physical measurement methods of data collection on a two bedroom self–contain floor plan building. The findings revealed that lesser construction time was required for IBs. It was also established from the study that a total cost of GH¢14,268.54 and GH¢ 18,869.64 were observed for IBs and SBs respectively. The difference in cost of SBs were found to be GH¢4,601.10, representing 24.38%. The consequence is reduction in laborer force, limited finishing time and minimum running cost, without compromising the aesthetic and strength value. The study therefore recommends the use of IBs for prospective building developers, entrepreneurs and individuals due to its cost saving, time and running cost.

Keywords: affordable housing, environmental friendliness, design flexibility, housing policy, housing problems, population, shelter

Introduction

The Ghanaian populace is facing serious housing problems, particularly for the poor who represent the majority of the Ghanaian population. Hence, adequate shelter is one of the most important basic human needs. Adewole1 posited that interlocking bricks are considered to have high energy efficiency, structural stability and a high acceptability index in terms of aesthetic as against the use of sandcrete blocks. Adedeji2 & Arayela3 opined that building materials constitutes the main factors and the largest single input in housing construction; restrict the supply of housing account for between 50–60 percent of building cost. Interlocking bricks (IB) have always been in use to a lesser extent; however, according to Ogunsemi,4 extensive studies on the technology appeared after the first ecological–villages came into being. The Interlocking Brick (IB) is a technology that developed the idea of dry stacking bricks during construction method known as mortar–less bricks. Sandcrete blocks as indicated by Akeem et al.5 is known as a walling unit produced from sand, cement and some water, and it is widely used in Ghana as a walling unit. Cement as a binder remains the most expensive input in the production of sandcrete blocks. The National Housing Policy of Ghana, as indicated by Gidigasu6 through the Ministry of Works and Housing in 1986 emphasized the development and use of local building material to contribute to the solution of the housing crises, thereby, reducing the importation of foreign building materials to a minimum. Its widespread use can be attributed to its availability and satisfactory characteristics.7

The accumulated housing deficit in Ghana as point out by Mustapha et al.8 was due to neglected use of the use of traditional building materials by developers. The influx of foreign building materials and techniques has also been a major problem facing the construction industry in Ghana. However, Nicco–Annan9 exposed the high cost and time overruns as well as poor quality of construction materials perceived to be associated with construction product delivery process in Ghana. This can only be resolved when the percentage cost difference in putting up a building using sandcrete blocks and interlocking bricks are known. Sarfoh10 posited that the cost of housing has soared out of control to the point that only few wealthy Ghanaians can afford to buy a house in the urban core. The paper compared the cost of sandcrete blocks (SBs) and interlocking bricks (IBs) for residential buildings in Ghana.

Methodology

The quantitative and case study approaches were adopted in this study to determine the comparative cost analysis between interlocking bricks (IBs) and sandcrete blocks (SBs) for residential buildings in Ghana. This was determined through the qualitative approach and physical measurements of a two–bedroom self–contain floor. The physical measurement of a two–bedroom self–contain house was conducted from the foundation through to the beam level. Prices of IBs and SBs were obtained from various building materials shops in the Cape Coast Metropolis in May 2016. The data collected as shown in Tables 1–10 were used to estimate the cost elements. While Tables 11–16 shows the unit costs of interlocking blocks (IBs) and sandcrete blocks (SBs). All these account for the difference between IBs and SBs, as well as their percentage cost difference. The information was also used to compare and contrast the cost benefit analysis in promoting affordable housing in Ghana. Descriptive statistics was used in the analysis of the data.

Literature review

Interlocking and sandcrete blocks

Both interlocking blocks and sandcrete blocks as shown serve similar purpose.11 The research report further indicated that both interlocking blocks and sandcrete blocks, as shown in Figures 1 and 2 have varied differences and similarities in terms of price, durability, choices, convenience, and their advantages over each other.11 Assiamah et al.12 in their study of interlocking and sandcrete blocks for building walling systems realized a 50% from the output of the masons when interlocking blocks were used as compared to sandcrete blocks. Material cost for the use of mortar by each mason for both interlocking blocks was lower than sandcrete blocks. Cost of labour also reduced drastically and this result concur with that of Danso et al.13 This is in relation to construction of walls. Assiamah et al.,12 posited that the reduction in cost was due to minimum mortar used during the construction. Assiamah et al.,12 concluded that the cycle time of bonding blocks in interlocking blocks reduced significantly and subsequently increased the speed of wall construction. Interlocking blocks are also affordable in terms of cost and weather conditions. The use of materials also was cut down significantly and labour cost reduced (Figure 1).

Figure 1 Sandcrete blocks.
Source Ghana Homes Block.11

A research by Ghana Homes Block11 show that the use of interlocking block has reduced drastically due to its limited use in the country. Even Ghana has a clay deposit in all the regions, but non patronization of the products of the industry has resulted to close of the brick industry in Ghana (Figure 2).

Figure 2 Interlocking blocks.
Source Ghana Homes Block.11

Findings

The cost estimates for both brick–work and block–work brickwork which comprised of materials, labor and finishing are presented in this section. The area of the building and one brick were found to be 148.71m2 and 0.023m respectively. The total number of blocks and bricks were found to be 148m2 and 6466. Twenty–five percent (2.5%) waste was added to obtain 162 blocks and 6628 bricks. One bag of cement was required to lay 44bricks within a 1m2 area and 9m2 area utilized 18bags of cement, 396 of blocks and 6628 of bricks with 0.85 waste. A mix ratio of 1:6 was used with a bag of cement; weighing 50kg and 18 bags of cement utilized 5400kg of aggregate. Water, cement ratio of 0.025 and 50kg, utilized 12.5kg of aggregate. An area of 80m3 with 20% (16 m3) utilized 96m3. The rendering process utilized a mix ratio of 1:4 and 72gallons of water and 63bags of cement (Tables 1-7). Table 4 presents cost of materials for blocks, which comprises of blocks, cement, fine aggregate (sand) and water.

Bricks

Amount

Bricks = GH 1.50 per 1

6628 bricks at GH 1.50

GH 9,942

Loading and offloading = GH 200 per 1000 bricks

200 1000 =0.2 MathType@MTEF@5@5@+= feaagKart1ev2aaatCvAUfeBSjuyZL2yd9gzLbvyNv2CaerbuLwBLn hiov2DGi1BTfMBaeXatLxBI9gBaerbd9wDYLwzYbItLDharqqtubsr 4rNCHbGeaGqiVCI8FfYJH8YrFfeuY=Hhbbf9v8qqaqFr0xc9pk0xbb a9q8WqFfeaY=biLkVcLq=JHqpepeea0=as0Fb9pgeaYRXxe9vr0=vr 0=vqpWqaaeaabiGaciaacaqabeaadaqaaqaaaOqaaKqbaoaalaaake aajugibiaaikdacaaIWaGaaGimaaGcbaqcLbsacaaIXaGaaGimaiaa icdacaaIWaaaaiabg2da9iaaicdacaGGUaGaaGOmaaaa@4002@
0.2 at 6628

GH 1,325

Total cost

GH 11,268

Cement

Cement = 18@ 32

GH 576.00

loading = 1.40@ 18

GH 25.20

Total cost

GH 601.20

Fine Aggregate (Sand)

 

Sand = 5.4m3 =5m3

GH 250.00

Water

 

Water = 72@ 1.00 72.00

GH 72.00

Cost of labour

 

Total number of bricks = 6628

Number of bricks lay per day is 800 (per one mason)

Therefore number of days that will be used = 6628 100 MathType@MTEF@5@5@+= feaagKart1ev2aaatCvAUfeBSjuyZL2yd9gzLbvyNv2CaerbuLwBLn hiov2DGi1BTfMBaeXatLxBI9gBaerbd9wDYLwzYbItLDharqqtubsr 4rNCHbGeaGqiVCI8FfYJH8YrFfeuY=Hhbbf9v8qqaqFr0xc9pk0xbb a9q8WqFfeaY=biLkVcLq=JHqpepeea0=as0Fb9pgeaYRXxe9vr0=vr 0=vqpWqaaeaabiGaciaacaqabeaadaqaaqaaaOqaaKqbaoaalaaake aajugibiaaiAdacaaI2aGaaGOmaiaaiIdaaOqaaKqzGeGaaGymaiaa icdacaaIWaaaaaaa@3CE8@

8days

Amount paid per day is 50 per mason and 40 per labour

Cost per mason = 8 x 50

GH 400

Cost per labour = 8x 40

GH 320

Finishing

 

Assume 1m3 for polishing = GH 3.21@ 422.91m3

GH 1357.54

Table 1 Cost of estimate for brickwork

Blocks

Quantity

Area of building = 138.41 m2

Area of one block = 0.104 m2

Total number of blocks = 138.41 m 2 0.104 m 2 MathType@MTEF@5@5@+= feaagKart1ev2aaatCvAUfeBSjuyZL2yd9gzLbvyNv2CaerbuLwBLn hiov2DGi1BTfMBaeXatLxBI9gBaerbd9wDYLwzYbItLDharqqtubsr 4rNCHbGeaGqiVCI8FfYJH8YrFfeuY=Hhbbf9v8qqaqFr0xc9pk0xbb a9q8WqFfeaY=biLkVcLq=JHqpepeea0=as0Fb9pgeaYRXxe9vr0=vr 0=vqpWqaaeaabiGaciaacaqabeaadaqaaqaaaOqaaKqbaoaalaaake aajugibabaaaaaaaaapeGaaGymaiaaiodacaaI4aGaaiOlaiaaisda caaIXaGaamyBaKqba+aadaahaaWcbeqaaKqzadWdbiaaikdaaaaak8 aabaqcLbsapeGaaGimaiaac6cacaaIXaGaaGimaiaaisdacaWGTbqc fa4damaaCaaaleqabaqcLbmapeGaaGOmaaaaaaaaaa@476A@

1,331 blocks

 5% per waste

67 blocks

Total number of blocks

1,398 blocks

Table 2 Cost estimates for block– work

1 bag of cement laying 50 blocks

Bags

Number of bag of cement = 1,398 50 MathType@MTEF@5@5@+= feaagKart1ev2aaatCvAUfeBSjuyZL2yd9gzLbvyNv2CaerbuLwBLn hiov2DGi1BTfMBaeXatLxBI9gBaerbd9wDYLwzYbItLDharqqtubsr 4rNCHbGeaGqiVCI8FfYJH8YrFfeuY=Hhbbf9v8qqaqFr0xc9pk0xbb a9q8WqFfeaY=biLkVcLq=JHqpepeea0=as0Fb9pgeaYRXxe9vr0=vr 0=vqpWqaaeaabiGaciaacaqabeaadaqaaqaaaOqaaKqbaoaalaaake aajugibabaaaaaaaaapeGaaGymaiaacYcacaaIZaGaaGyoaiaaiIda aOWdaeaajugib8qacaaI1aGaaGimaaaaaaa@3D20@

30 bags

 5% of waste

2 bags

Total number of cement in bags

32 bags

Fine aggregate (sand)

A mix ratio of 1: 4

A bag of cement

50kg

Four (4) parts of sand = 200kg (20 x 4)

200 kg x 32

6,400kg

1 m3

1,000kg

6400 1000 ×1 m 2 MathType@MTEF@5@5@+= feaagKart1ev2aaatCvAUfeBSjuyZL2yd9gzLbvyNv2CaerbuLwBLn hiov2DGi1BTfMBaeXatLxBI9gBaerbd9wDYLwzYbItLDharqqtubsr 4rNCHbGeaGqiVCI8FfYJH8YrFfeuY=Hhbbf9v8qqaqFr0xc9pk0xbb a9q8WqFfeaY=biLkVcLq=JHqpepeea0=as0Fb9pgeaYRXxe9vr0=vr 0=vqpWqaaeaabiGaciaacaqabeaadaqaaqaaaOqaaKqbaoaalaaake aajugibabaaaaaaaaapeGaaGOnaiaaisdacaaIWaGaaGimaaGcpaqa aKqzGeWdbiaaigdacaaIWaGaaGimaiaaicdaaaaccaWdaiab=Dna0k aaigdacaWGTbWcdaahaaadbeqaaiaaikdaaaaaaa@42A0@

6.4 m3

Water

Water cement ratio of 0.5 = Water = 0.5

 50kg

Weight of Water = 50 kg x 0.5

25kg

  = 1000kg 25kg ×1 m 3 MathType@MTEF@5@5@+= feaagKart1ev2aaatCvAUfeBSjuyZL2yd9gzLbvyNv2CaerbuLwBLn hiov2DGi1BTfMBaeXatLxBI9gBaerbd9wDYLwzYbItLDharqqtubsr 4rNCHbGeaGqiVCI8FfYJH8YrFfeuY=Hhbbf9v8qqaqFr0xc9pk0xbb a9q8WqFfeaY=biLkVcLq=JHqpepeea0=as0Fb9pgeaYRXxe9vr0=vr 0=vqpWqaaeaabiGaciaacaqabeaadaqaaqaaaOqaaKqzGeGaeyypa0 tcfa4aaSaaaOqaaKqzGeaeaaaaaaaaa8qacaaIXaGaaGimaiaaicda caaIWaGaam4AaiaadEgaaOWdaeaajugib8qacaaIYaGaaGynaiaadU gacaWGNbaaaGGaa8aacqWFxdaTcaaIXaGaamyBaSWaaWbaaWqabeaa caaIZaaaaaaa@4677@

40 m3

20% for waste

8 m3

Total volume for waste

48m3

25m3 = 1 gallon (big size)

48 m 3 25 m 3 =1.92m MathType@MTEF@5@5@+= feaagKart1ev2aaatCvAUfeBSjuyZL2yd9gzLbvyNv2CaerbuLwBLn hiov2DGi1BTfMBaeXatLxBI9gBaerbd9wDYLwzYbItLDharqqtubsr 4rNCHbGeaGqiVCI8FfYJH8YrFfeuY=Hhbbf9v8qqaqFr0xc9pk0xbb a9q8WqFfeaY=biLkVcLq=JHqpepeea0=as0Fb9pgeaYRXxe9vr0=vr 0=vqpWqaaeaabiGaciaacaqabeaadaqaaqaaaOqaaKqbaoaalaaake aajugibabaaaaaaaaapeGaaGinaiaaiIdacaWGTbWcdaahaaadbeqa aiaaiodaaaaak8aabaqcLbsapeGaaGOmaiaaiwdacaWGTbWcdaahaa adbeqaaiaaiodaaaaaaKqzGeWdaiabg2da9iaaigdacaGGUaGaaGyo aiaaikdacaWGTbaaaa@4447@

2 gallons (50 litres)

Table 3 Cement

Description

Blocks

Amount (GH¢)

Blocks =

GH¢2.50 per block

Therefore 1,398 blocks@ GH¢ 2.50

GH¢ 3,495.00

T&T/ loading and offloading GH¢0.40/block

GH¢ 559.20

Total cost

GH¢ 3,550.20

Cement

Cement = 32bags@ GH¢ 32.00

GH¢ 1,024

T&T/loading and offloading = GH¢ 1.40@ 32 bags

GH¢ 45.00

Total cost

GH¢ 1,069.00

Fine aggregate (sand)

Sand = 6.4m3 = 6m3@ GH¢ 41.67/ m3

GH¢ 250.00

Water

Water = 64gal.@ GH¢ 1.00

GH¢ 64.00

Table 4 Cost of blocks and bricks

Total number of blocks to be laid

1,398 blocks

Number of blocks lay per day per mason

80 blocks

Therefore number of days that will be used = 1,398 blocks 80 blocks MathType@MTEF@5@5@+= feaagKart1ev2aaatCvAUfeBSjuyZL2yd9gzLbvyNv2CaerbuLwBLn hiov2DGi1BTfMBaeXatLxBI9gBaerbd9wDYLwzYbItLDharqqtubsr 4rNCHbGeaGqiVCI8FfYJH8YrFfeuY=Hhbbf9v8qqaqFr0xc9pk0xbb a9q8WqFfeaY=biLkVcLq=JHqpepeea0=as0Fb9pgeaYRXxe9vr0=vr 0=vqpWqaaeaabiGaciaacaqabeaadaqaaqaaaOqaaKqbaoaalaaake aajugibabaaaaaaaaapeGaaGymaiaacYcacaaIZaGaaGyoaiaaiIda caGGGcGaaiOyaiaacYgacaGGVbGaai4yaiaacUgacaGGZbaak8aaba qcLbsapeGaaGioaiaaicdacaGGGcGaamOyaiaadYgacaWGVbGaam4y aiaadUgacaWGZbaaaaaa@4A9D@

18days

Amount paid per day = GH¢ 50.00 per mason

Amount paid per day = GH¢ 40.00 per labour

Cost per mason = 18days@ GH¢ 50.00/day

GH¢ 900.00

Cost per labour = 18days@ GH¢ 40.00/day

GH¢ 720.00

Total cost

GH¢ 1,620.00

Concrete works (Tie– Beam)

Plain in– situ concrete (1:3:6) in lintel

GH¢ 295.1 per m3

Volume of concrete for lintel = 3.1m3@ GH¢ 295.1

GH¢ 914.81

Form work

Surface area formwork = 41.2m2

GH¢ 824.00

Therefore area of formwork = 41.2m2@ GH 20

Table 5 Cost of labour

Fine aggregate (sand) for plastering

Where 1m3= 1.484m3

Therefore 7.55m3 @ 1.484m3

11.204 m3

Fine aggregate (sand) for rendering

Where 1m3 = 1.39m3

Therefore 3.03m3 @ 1.39m3 =

4.212 m3

Total volume of sand

15.42 m3

Add 5% for waste

0.771 m3

Total

16.20 m3

Table 6 Aggregate for plastering and rendering (sand)

Fine aggregate (sand)

Assume 6m3 truck capacity= GH 250.00

GH 250.00

Therefore 16.20m3/6 m3@ GH 250

GH 675.00

Cement

GH 32.00@100 bags

GH 3200.00

Labor cost

 

Assume a mason per day = 3 days

Therefore 100 bags/3 days = 33 days

33 days

Assume GH 40/ mason/day@33 days

GH 1320.00

Assume GH 30/labour/day@33 days

GH 990.00

Total cost

GH 2310.00

Water for plastering

Assume 1 bag of cement = 2 gallons (50 litres)

Therefore 100 bags at 2 gallons = 200 gallons

Assume a gallon = GH 1.00

Therefore 200 gallons @ 1.00

 GH 200.00

Total cost

GH 6385.00

Table 7 Cost of finishing

This section presents the discussions on the unit cost and the cost per the area of a single storey two bedroom self–contained using IBs and SBs to determine their cost difference. It begins with the unit cost of IBs and followed by SBs to determine cost of materials and labor. Tables 8–10 present the unit cost of interlocking blocks, comprising of material cost, labor cost and finishes.

The mix ratio was 1:6 (one part of ordinary Portland cement to
six parts of sand)

Amount GH¢

The total number of IBs required was

6,628 bricks

The cost per IBs was

1.5

Therefore 6,628 bricks@ GH¢1.50p

9,942.00

Transport and loading/off– loading: GH¢200.00 per 1000 bricks

1,325.00

Cost of cement: 18bags@ GH¢32.00

576

Transport and loading/off– loading: GH¢1.40p@ 18 bags

25.2

Cost of Sand: 5m3

250

Cost of water: 72gallons (25litres/gal.)@ GH¢ 1.00

72

Total Material Cost

12,191.00

Table 8 Material cost (MC)

Total surface area:

422.91m2

Cost per m2 for polishing

3.21

Total cost of polishing: – GH¢3.21 @ 422.91m2

1,357.54

Grand total cost of A, B and C

14,268.54

Table 9 Labor cost (LC)

Mix ratio was 1:4 (one of ordinary Portland
cement to four head pans of sharp sand)

GH¢

The total number of sandcrete blocks required was

1,398 blocks

Cost per sandcrete blocks:

2.5

Therefore 1,398 blocks@ GH¢2.50

3,495.00

Add T&T and loading/off– loading:– GH¢0.40 @ 1398blocks

559.2

Cost of cement:– 32bags@ GH¢32.00

1,024.00

Add T&T and loading/off– loading:– GH¢1.40p @ 32bags

44.8

Cost of Sand = 6m3@

250

Cost of water = 64 gallons (25litres/gal)@ GH¢ 1.00

64

Cost for concrete works: – GH¢295.1@ 3.1m3

914.81

Cost for form works: – GH¢20.00@ 41.2m2

824

Total Material Cost

7,175.81

Table 10 Material cost (MC)

Unit cost of sandcrete blocks (SBS)

Tables 11-13 present unit cost of sandcrete blocks, comprising of material cost, labor cost and finishes.

The labour cost per mason: GH¢50.00@ 18 days

900

The labour cost per 2 labourers: GH¢80.00@ 18 days

1,440.00

Total labour cost

2,340.00

Table 11 Labor cost (LC)

Plastering (P) and Rendering (R)

Cost of cement = 100bags × GH¢ 32.00.

3,200.00

Cost of sand = 16.20m3/6m3@ GH¢ 250.00

675

Cost of water = 200gallons (25litres/gal)@ GH¢ 1.00

200

Labour cost per mason = GH¢ 40.00 for 33days

1,320.00

Labour cost per labourer – GH¢ 30@ 33days

990

Total cost for P & R (a)

6,385.00

Painting works

 

Total surface area to be painted: 422.91 m2

Total Cost of painting per m2 (b)422.91 m2@ GH¢7.02/ m2

2,968.83

Total cost of finishes (a) and (b)

9,353.83

Grand total cost of I, II and III

GH¢ 18,869.64

Table 12 Finishes
a – Total cost of plastering and rendering
b – Total cost of painting per m2
I – Total cost of materials; II – Total cost of labor; III – Total cost of finishes (a) and (b)

Percentage cost difference between IBS and SBS block for residential buildings

Table 14 presents the percentage cost difference between IBs and SBs.

IBs

Total cost (GH¢)

SBs

Total cost (GH¢)

Cost diff. (GH¢)

% Cost diff.

Material cost

12,191.00

Material cost

7,175.81

5,015.19

41.14%

Labor cost

720

Labor cost

2,340.00

1,620.00

69.23%

Finishing cost

1,357.54

Finishing cost

9,353.83

7,996.29

85.49%

Total Cost

14,268.54

Total Cost

18,869.64

4,601.10

24.30%

Table 13 Percentage cost difference between IBs and SBs

Discussion

This section presents the discussions on the cost of element which account for the difference. shows that comparative cost of interlocking bricks and sandcrete blocks were obtained by estimating for the cost of a two bedroom single–storey self–contained building plan excluding the roof and substructure. The prices of interlocking bricks and sandcrete blocks were obtained from the market. Sandcrete blocks (450x225x150) were sold at GH¢ 2.90, whiles interlocking bricks (250x125x100) mm were sold at GH¢ 1.70. The cost includes loading/off–loading and transportation. It was observed from the findings that the use of IBs required only 18 bags of cement for the total of 6,628bricks, while 1,398 SBs required 132 bags of cement for both block–laying works, plastering and rendering for the completion of single–storey two– bedroom self–contained bungalow. The use of IBs required only 5m3 of sand costing GH¢250.00/6m3, while the use of SBs required a total of 22.20m3 for block–laying work, plastering and rendering costing GH¢925.00. Additionally, a gang of one mason plus one laborer may possibly lay between 800–1000 IBs per day, thereby using only 8 days in laying a total of 6,628 IBs with a labor cost of GH¢ 720.00. On the other hand, a gang of 1mason plus 2 labor could rather be used in 18 days in laying 1,398 SBs costing a total of GH¢2,340.00 for labor. In the case of finishing, IBs do not require any painting unless the user for no apparent reason decides to do so. Nonetheless, a chemical known as PVC bond is applied as a polish to the surface which cost GH¢ 3.21 per m2, hence a total of GH¢1,357.54 is required for the finishing. On the other hand, GH¢ 5.40 per m2 is required for SBs which translates into a total cost of GH¢ 9,353.83 for painting.

Discussion on percentage cost difference between interlocking bricks and sandcrete blocks

The total material cost for IBs was GH¢12,291.00 while SBs was GH¢7,175.81 making a cost and percentage difference of GH¢5,015.19 and 41.14% respectively (Table 14). Labor cost for both IBs and SBs was GH¢720.00 and GH¢2,340.00 which makes the cost difference of GH¢1,620.00 and the percentage cost difference of 69.23%. In the case of finishes, the total cost of IBs was GH¢1,357.54 while SBs was GH¢9,353.83 which also makes the cost and percentage cost difference of GH¢7,996.29 and 85.49%, respectively. On a whole, the total cost of IBs was GH¢14,268.54 while that of SBs was added up to get GH¢ 18,869.64. The finishing cost for IBs was higher than the material cost and least among the three was labor cost. However, the cost difference as well as the percentage cost difference was established to be GH¢4,601.1 and of 24.38%. This shows that constructing with IBs is cheaper than that of SBs. Despite the fact that material cost for IBs is more than SBs, there is also an indication that the labor and finishing cost are more when you consider the use of SBs. Assiamah et al.,12 has also attested to the fact that interlocking blocks are more economical than sandcrete blocks. They further indicated that have the potential of supporting the affordable housing concept in Ghana.

Conclusion

The results revealed that the cost incurred in the use of interlocking bricks for construction of the proposed two bedroom single–storey self–contained building plan under study was cheaper than using sandcrete blocks for construction of the same building in terms of material and labor cost. Considering the cost elements which account for the difference, the study further revealed that the use of sandcrete blocks requires mortar for the laying of blocks as well as associated non–contributory activities like sorting, taking, breaking, laying and leveling of blocks as well as taking, mixing, laying and spreading of mortar and finally, waiting for materials. All of these affect the cost as well as the net output. Hence, these activities together with the use of mortar are eliminated in the use of interlocking bricks. There is flexibility in the design, environmental friendliness reduction in the time for setting operation and elimination of associated wastage. There is also cost saving in the case of IBs at GH¢14,268.54 and SBs at GH¢ 18,869.64. The percentage in the cost difference was established to be GH¢4,601.1 and of 24.38%, respectively, without compromising the aesthetic and strength quality. Interlocking bricks have been found to be better alternatives to sandcrete blocks and should, therefore, be used to promote affordable housing delivery in Ghana for building developers. This will facilitate cost efficiency and make housing provision available and more affordable.

Acknowledgement

The authors wish to acknowledge the effort of the laboratory technicians at Building Technology Department, Cape Coast Technical University, Cape Coast. Ghana.

Conflicts of interest

The author declares there is no conflict of interest.

References

  1. Adewole HA. Building Materials in South Western Nigeria (Affordability In Building Construction Through The Use of Interlocking Bricks). Department of Architecture, Federal University of Technology, Akure, Nigeria; 2008.
  2. Adedeji YMD. Technology and standardized composite cement fibres for housing in Nigeria. J Niger Inst Archit. 2010;1:19–24.
  3. Arayela O. Laterite bricks: before now and hereafter. Inaugural lecture series 40 delivered at Federal University of Technology, Akure. 2005;5–15.
  4. Ogunsemi DR. The use of enough quality and quantity materials for building a durable edifice. A Lecture delivered at Campus Transformation Network, Federal University of Technology, Akure, Nigeria; 2010.
  5. Akeem AR, Ayodeji KM, Aliu AS. Comparative Analysis of Sandcrete Hollow Blocks and Laterite Interlocking Blocks as Walling Elements. International Journal of Sustainable Construction Engineering & Technology. 2012;3(1):79–88.
  6. Gidigasu MD. Lateritic soil construction for housing in Ghana. Journal of the Ghana Institution of Engineers. 2005;3(2).
  7. Andam AK. Bricks, blocks and the future administrative capital of Ghana. A report delivered during the Inaugural lecture of the Ghana Academy of Arts and Sciences. Accra, Ghana; 2004.
  8. Mustapha Z, Akani M. Earthen Construction, as a Solution to Building Industries in Ghana. Department of Building Technology, School of Engineering, Cape Coast Polytechnic Cape Coast. Journal of Economics and Sustainable Development. 2013;4(3):190–198.
  9. Nicco–Annan J. Partnering in Construction. The Quantity Surveyor, 2006;1:14–19.
  10. Sarfoh O. Brief History of Housing in Ghana; 2007.
  11. Ghana Homes Block. The Price of Building Blocks & Bricks in Ghana; 2014.
  12. Assiamah S, Abeka H, Agyeman S. Comparative study of interlocking and sandcrete blocks for building walling systems. International Journal of Research in Engineering and Technology (IJRET). 2016;2319–1163.
  13. Danso H, Manu D. High cost of materials and acquisition problems in the construction industry in Ghana. International Journal of Research in Engineering & Applied Sciences (IJREAS), 2013;3(3):18–33.
Creative Commons Attribution License

©2018 Jackson, et al. This is an open access article distributed under the terms of the, which permits unrestricted use, distribution, and build upon your work non-commercially.